California Bullet Train Costs Soar to $77B; Opening Delayed

FILE - In this Feb. 18, 2016, file photo, Dan Richard, chairman of the board that oversees the California High-Speed Rail Authority, gestures to a map showing the proposed initial construction of the bullet train in the revised business plan in Sacramento, Calif. The California High-Speed Rail Authority will release its latest business plan for the bullet train, which has been beset by delays and cost increases, Friday March 9, 2018. (AP Photo/Rich Pedroncelli, file)

SACRAMENTO, Calif. — The projected cost of California’s bullet train between San Francisco and Los Angeles has jumped to $77 billion and the opening date has been pushed back four years to 2033, according to a business plan released Friday.

The two-year plan presented by the California High-Speed Rail Authority is the first under new chief executive Brian Kelly, who has promised more transparency about the project’s challenges after years of cost increases and delays.

While the goal is to connect the two major cities, the new plan focuses primarily on opening track between San Francisco and the Central Valley, an agriculturally dominant, less-populated portion of inland California. That portion of track is now set to be finished by 2029, also marking a four-year delay, and significant challenges remain.

One of them is how to cross through a section of mountains — a critical segment to link Silicon Valley to the Central Valley. Rail officials are still working on how best to do that, Kelly wrote in the plan’s introduction.

The $77 billion cost, a 20 percent increase, is a baseline estimate, but Kelly also included high and low ranges in the plan based on potential risks.

It says 119 miles (192 kilometers) of track in the Central Valley, the first construction segment, is scheduled to be completed by 2022. That’s 14 years after voters approved a $10 billion bond for high-speed rail in November 2008.

A summary of the plan reviewed by The Associated Press offers limited details on the portion between Central Valley and Los Angeles. The agency hopes to complete all necessary environmental reviews for the entire line by 2022, a delay from initial timelines that planned for environmental clearance by 2017 for most parts of the track.

How to pay for the entire project remains “uncertain,” Kelly said.

The state has spent $2.5 billion in federal stimulus money and has an additional $930 million in federal money on the table. That’s on top of the $10 billion bond from voters.

The rest of the money comes from California’s cap-and-trade auctions, a system meant to limit carbon emissions by selling credits to pollute and a volatile source of revenue that can be diverted by lawmakers in the future. Predicted private investment has not come in either.



This story has been corrected to show the 119 miles of track in the Central Valley is the first construction segment, not the first operational segment.



You can be the first one to leave a comment.

Leave a Comment


News Sources

  • ABC
  • Access Hollywood
  • Associated Press
  • BBC
  • Bloomberg
  • Boston Globe
  • C-SPAN
  • CBS
  • Chicago Sun-Times
  • Christian Science Monitor
  • Center for Public Integrity
  • CNN
  • Congressional Quarterly
  • Democracy Now!
  • Digg
  • E! Online
  • Entertainment Weekly
  • Financial Times
  • Forbes
  • Foreign Policy
  • Fortune
  • Front Street Magazine

  • U.S. News, World News
  • Business, Politics
  • Entertainment, Sports
  • Art, Lifestyle
  • Videos And More
  • News Sources

  • Fox News
  • Google News
  • Guardian
  • Huffington Post
  • Independent
  • LA Weekly
  • Los Angeles Times
  • McClatchy
  • Mother Jones
  • National Journal
  • NBC New
  • New York Post
  • New York Times
  • Newsweek
  • Newsy
  • NPR
  • PBS NewsHour
  • People
  • Politico
  • Reuters
  • TPM
  • Washington Post
  • Thanks For Your Support!


    Copyright © 2018 Front Street. All Rights Reserved.